KGVPF Development: Phase One Begins
March 3, 2025Crewe FC, as the appointed Football Development Partner of Cheshire East Council, have today begun the first phase of construction work at the King George V Playing Field.
The initial phase of works will be undertaken by Masons Build on behalf of the Club and will initially focus on the redevelopment and improvement of the KGVPF Changing Pavilion.
The changes to the building will see the modernisation of changing rooms, the creation of a multi-functional social suite, bar and kitchen, along with the installation of a disability platform lift to make the building fully accessible to all.
The internal building works are expected to take between 8-12 weeks to complete, with the construction of the new artificial grass pitch expected to commence in April.